Now the project we were undertaking was a 24X32' cabin with a 8X20' screened in porch. As you will see in the numerous pictures to follow, vinyl siding, fascia and soffiting, and steel roofing composed the exterior. Now with this information reader, what is your guess for our construction project? Two days? Ten days? Remember this is for finishing the exterior only. I'll let the pictures do the majority of the story telling. *Note: I flew all building equipment i.e. hammers, skill saws, miter saws, generator in prior to building so construction was ready to begin upon arrival.
Predictions:
Dad: 5 days Benny: 7 days Corey: 8 days Tyrol: 9 days Nathan (the pessimist): 12 days
Day 1
Our first day of construction began with flying into Burnt around 7 am with the 1/2 the crew (Dad, Corey and Tyrol). However, I was required to promptly fly to Sandy to pick up the brains of the operation, Benny, along with a load of knotty pine interior siding. Concrete pads were measured out with pressure treated posts as the foundation of the cabin. Production moved swiftly as we were able to finished the entire floor of the cabin and even started framing one of the walls.
Day 2
The amazingly warm weather greeted us for another day. The weather was perfect for building a cabin 80 degrees and no winds. Ok, it was a tad warm but I'll never complain about 80 degree weather in September in the Big Hook area. The goal for day two was finish building trusses and complete the framing of the walls.
Three of us tackled creating a jig for the trusses while Dad and Benny laid out walls for the floor plan. After another 10 hour day we managed to finish hand constructing the trusses thanks to the pre-cut boards, however the trusses and gable ends chewed up most of the time. All walls were framed although only three walls were erected with OBS boards placed on most.
Day 3
The unreal weather continued however black flies and mosquito's began hatching. The construction paced slowed this day due to hot humid weather peaking at 90 degrees. With rain in the days to come we really pushed to get the roof in place. We came really close to our goal and managed to install all the rafters with strapping. The remainder of the cabin was enclosed with OBS plywood. With an hour left in the day we began securing the steel roofing. Unfortunately daylight got the better of us and we only finished half of the roof.
Day 4
Poor weather slowed us this day. Rain and metal roofing are a unfavorable combination. We held off finishing the roof and focused on a new set of stairs for the camp. We also began constructing the screened in porch.
Day 5
Clearing weather allowed us a daybreak start. The roofing was completed along with great progress on the fascia and soffiting. The windows and door were installed. The new large windows are a enormous improvement allowing ample amounts of light in. Everyone noticed the undergrowth sprouting all over the forest bed. Grass on the front lawn was already ankle high. We ended the day once again sun burnt and sweltering in heat.
Day 6
The task for this day was to tackle the vinyl siding. After a round of camp checks I joined Corey and Tyrol with the siding while Dad and Benny focused on finishing the porch. We finished the vinyl siding in no time and I began siding the interior with the knotty pine. Once again the weather cooperated with sunny skies and warm temperatures. We started to notice wildlife in the woods. Wood peckers and robins chirped from the burnt trees. We even spotted a moose on the south shoreline.
Day 7
If you guessed seven days to finish an outpost cabin exterior you are indeed correct. Below is a photo of the area right after the forest fire and a picture of the completed exterior. Basically 70 hours of work with a full time 4 man crew and one part timer completed the exterior on the project. Tremendous weather aided the building process.
Before After
Below are couple pictures of the interior of Burnt Lake.
The interior of the cabin will include two 12x12' bedrooms and an 8x12 shower room with a vanity. The kitchen and sitting area is a massive 12x32' area. All the rooms have doors and ceilings. The cabin will be powered with a quiet and efficient Honda 2000 Watt generator.
All in all, the construction of an outpost camp 200 miles from the nearest road was quite the learning experience. We did have some hiccups but overall the process went along smoothly. The weather cooperated, our preplanning efforts kept the errors to a minimum and most of all, we had a great group of guys working incredibly hard every single day.
Good luck on the water this fall everyone!
-Nathan
-Nathan
Big Hook Camps
www.bighookcamps.com